basement construction in Sheen, Richmond Park

Pile beam underpinning, facade retention, basement construction inside a secant piled coffer dam. De-watering was also required as it had a river (Beverly Brook) running underneath it.

To see the finished job please click here:

http://www.gpflewis.co.uk/portfolio/fife-road-richmond-park

  • Location: Sheen, Richmond Park
  • Date: 03/12/2010
  • Duration: 14 months
  • Cost: £400k

Facade retention of the front of the house before excavation of the basement.

Facade retention of the front of the house before excavation of the basement.

Excavation.

Excavation with pile beam underpinning.

Steel beams for temporary works.

Temporary works to hold existing roof in place.

Reinforcement.

Formwork.

Formwork.

Concrete to slab.

Formwork and structural steel.

Temporary works to hold existing roof in place.